The Honest Timeline
When clients ask how long their pergola will take, I give them the full picture—not just the construction time.
Complete Timeline Overview
| Phase | Duration |
| Quote & Design | 1-2 weeks |
| Permit Approval | 2-4 weeks |
| Material Order | 1-2 weeks |
| Construction | 2-5 days |
| Total | 6-12 weeks |
Phase 1: Quote & Design (1-2 Weeks)
- Site visit and measurements
- Design consultation
- Detailed quote preparation
- Revisions if needed
- Contract signing
Phase 2: Permit Approval (2-4 Weeks)
- Engineering drawings prepared
- Building permit application lodged
- Surveyor review
- Approval issued
Phase 3: Material Order (1-2 Weeks)
- Materials ordered from suppliers
- Custom cuts and powder coating
- Delivery scheduled
Phase 4: Construction (2-5 Days)
The actual build is quick:
- Day 1: Footings and posts
- Day 2: Beams and framework
- Day 3: Roofing installation
- Day 4: Flashings and finishing
- Day 5: Cleanup and handover
What Can Cause Delays?
- Wet weather (can't pour concrete)
- Permit complications
- Material supply issues
- Access difficulties
- Unforeseen site conditions
How We Minimise Delays
At Undercover Concepts, we:
- Maintain relationships with fast suppliers
- Use experienced permit expediters
- Schedule around weather forecasts
- Communicate proactively about any delays